Shoring and Bulk excavation works at 100 Castlereagh Street Liverpool have been completed and construction of the super-structure is now well underway. Our shoring solution went down four levels and each basement footprint is just over 3350m2 each. The team from Ghossayn Group carried out the works with military precision and expertise and ACSES Engineers are proud to be part of the Design Team and honoured to be involved in such an excellent development.

100 Castlereagh Street Liverpool Image 1

Here is the 3D perspective.

About George Khalil

Principal Engineer with over 20 years experience encompassing business development, complex project management and technical design positions. Comprehensive knowledge of design standards and codes.