Structural Steel Rectification On Existing Buildings
When existing steelwork falls short of the strength it needs, rectification brings it back, through an assessment of what is there, a repair design and supervised work on site. The cause can be a fabrication mistake, a member cut or drilled after handover, corrosion, or a new load the frame was never designed for, and the first step is working out which one you are dealing with.
Our rectification work includes steelwork at Bonnyrigg Heights Public School, the rectification and extension of a steel roof and its supports on Australia Avenue at Olympic Park, and the redesign and rectification of an industrial building at Huntingwood.
The usual causes
Some problems are built in. Members get swapped, welds come out smaller than drawn, bolts are left loose or missing, and holes in the wrong place get reamed out on site until they fit.
Others arrive later. A purlin gets cut for a skylight, a brace comes out to fit a roller door, or a hole is flame-cut through a beam web for a pipe, the case covered in [web openings in steel beams for services](/blog/web-openings-in-steel-beams-for-services). New loads arrive the same way, with solar panels, plant or a hoist hung from a roof beam, all of which need the check described in [rooftop solar and plant](/blog/rooftop-solar-and-plant-structural-adequacy).
Corrosion is the slow one. It starts where water sits, at column bases buried in a slab, along box gutters, and in connections that trap moisture.
The steel as built
Rectification starts with the steel as built, because the drawings, if any exist, only show what was intended. We measure the sections, check the connections, count the bolts and look at the welds.
Where a weld carries real load, non-destructive testing such as ultrasonic or magnetic particle testing shows whether it is sound below the surface. Corrosion gets measured rather than judged by eye. Surface rust often looks worse than it is, while pitting under paint can be worse than it looks, and the remaining thickness of a flange is what decides its capacity.
The capacity check
The frame is then modelled as built and checked to AS 4100 for the loads it carries now, including any new plant or panels. Sometimes the frame turns out adequate and the repair is limited to a few connections. Sometimes a whole line of rafters needs strengthening.
The repair design
The repair depends on access as much as strength. Plates welded to a flange add section, a new member bolted alongside an old one shares its load, extra bolts or a new cleat replace a poor connection, and badly corroded members come out and get replaced.
Welding onto a loaded member is a different exercise from welding in a workshop. Heat lowers the strength of the steel near the weld while it is laid, so the member is often propped or unloaded first, and the welding sequence goes on the drawings. Site welds are specified and inspected to AS/NZS 1554.1, the same as workshop welds, and connection detailing follows the approach in [steel connections and shop drawings](/blog/steel-connection-design-and-shop-drawings).
Bolted repairs avoid hot work, which matters in an occupied building or near anything flammable, so we use them wherever the connection allows.
Repairs to the coating
Welding and grinding destroy the coating where they happen. Galvanised steel gets repaired with a zinc-rich paint, painted steel gets its paint system reinstated, and the options are set out in [corrosion protection for structural steel](/blog/corrosion-protection-for-structural-steel). Skip that step and the rectified area becomes the next place to corrode.
A building that is still in use
Rectification usually happens with the building occupied, whether that is a school, a warehouse with stock on the racks or an office. The work is staged so each part of the frame stays supported, with temporary props where a member is being replaced, and hot work is controlled with permits and a fire watch.
How we approach it
We start with the steel as it actually stands, then design the smallest repair that brings it back to full capacity. On site, we inspect the repair as it is carried out, because a fix welded or bolted differently from the drawing is simply a new defect.
The repair that holds is the one designed for the steel that is actually there.
ACSES provides structural engineering, including assessment and remediation design for existing buildings, across Sydney. Talk to us about a project.