Structural Engineering For Modular Buildings
Every stage of a modular building's life needs its own structural check: the module on the factory floor, on the back of a truck, hanging from a crane and stacked in the finished building. Each stage puts different forces through the frame, and the module has to survive all of them before anyone lives in it.
We work with builders on modular and prefabricated designs, and the structural thinking differs from a frame poured in place. The building still has to meet the same standards. What changes is the number of load cases, and how much depends on the connections.
Volumetric and panel systems
Volumetric modules are whole rooms, built as boxes with a floor, walls and a ceiling, then stacked on site. Panel systems arrive as flat wall and floor panels, which are stood up on the slab, braced while they are loose and then joined together into a frame that only becomes stable once the last connection is made.
Both are designed under the NCC for the class of building they form, to the same Australian Standards as any other building of that class. We design a steel module to AS 4100, or to AS/NZS 4600 where its sections are cold-formed, while a timber module follows AS 1720.1 and a concrete one AS 3600.
Lifting and transport
A module is lifted from set points, and its frame has to carry its own weight and all its finishes hanging from those points, with an allowance for the jolt as the crane takes the load. On the road it sees vibration, braking and cornering. A module that cracks its linings in transit arrives already damaged, so the frame is stiffened for the trip as well as for the building.
The size a module can be is set by what can travel by road, and that limit comes back into the floor plan early.
Load paths in the stack
Once stacked, the weight of the upper modules comes down through the corner posts or the walls of the modules below. Each module bears on the next at set points, through bearing plates or pads, and the loads have to line up all the way to the ground.
Small errors in level add up storey by storey in a tall stack. So tolerances are set for every lift and checked as the modules go in, the same discipline described in [precast connections and site tolerances](/blog/precast-connections-and-site-tolerances).
Connections between modules
Modules are tied to each other horizontally and vertically, so the building acts as one structure, not as a stack of separate boxes. Those ties also give the building a way to hold together if one module is damaged, the subject of [disproportionate collapse and tying requirements](/blog/disproportionate-collapse-and-tying-requirements).
Stability
Wind under AS/NZS 1170.2 and earthquake under AS 1170.4 push a building sideways, and a stack of modules needs a system to resist that push. Height changes the answer. In low-rise work, braced modules can do it themselves, with the floors acting as diaphragms that carry the load across to the braced walls, as explained in [diaphragm action and how floors brace a building](/blog/diaphragm-action-and-how-floors-brace-a-building). Taller modular buildings usually stand around a concrete core or a braced frame that takes the sideways load.
The work still done on site
The footings, the ground floor slab or podium and any basement are still built in place. Modules land on cast-in plates or bolts, and those have to be within tolerance, because a box made in a factory doesn't adjust on site the way formwork does.
The crane needs firm ground too. It stands on the site, often beside an excavation or on fresh fill, and its outrigger or track loads need checking before the first lift, as covered in [working platforms for piling rigs and cranes](/blog/working-platforms-for-piling-rigs-and-cranes).
Fire and sound
Each volumetric module has its own floor and its own ceiling, so two layers separate one module from the next, which helps with both sound and fire separation. The fire engineer and the acoustic consultant set those requirements, and the gaps between modules are detailed so the separation stays continuous.
An earlier design freeze
The factory builds while the site is still being prepared, so the design has to be settled earlier than for a poured frame. Moving a column or a service riser after modules are in production means rework in the factory, and it costs far more there than a change on paper.
How we approach it
We design the module, its connections and the ground it lands on as one structure, checked for the lift, the trip and the finished building. The site set-out and the module drawings come from the same dimensions, so the plates cast into the slab match the frames built in the factory.
A module goes into the building once, so the design has to be right before it leaves the factory.
ACSES provides structural engineering for modular and prefabricated buildings across Sydney. Talk to us about a project.