Stressing A Post-Tensioned Slab On Site

George KhalilFounder & Principal Engineer5 min read

Stressing is the moment a post-tensioned slab starts working the way it was designed. Until then, it is a lightly reinforced slab sitting on props, and the steps between the pour and the stressing decide whether it ends up as strong as the drawings say.

We design post-tensioned floors to AS 3600, with strand supplied to AS/NZS 4672, on projects such as the Maroubra Road apartments in Maroubra and Sierra Apartments in Crows Nest. Site reviews during post-tensioning are part of our construction phase services.

Before the pour

The tendons are strands of high-strength steel inside flat ducts, sitting on bar chairs set to the heights drawn on the post-tensioning drawings. That profile is the design. Each tendon sits high over the columns and low in the middle of the span, and a tendon set low over a column gives less lift exactly where the slab needs it most.

The pre-pour inspection checks the tendon heights, the anchorages at the slab edge and the extra reinforcement behind each anchorage, which spreads its large force into the concrete. The ducts are taped and sealed, so cement paste can't leak in during the pour and block them. The wider inspection is covered in [pre-pour inspections](/blog/construction-supervision-pre-pour-inspections).

Concrete strength before stressing

The post-tensioning drawings state the concrete strength needed before stressing. Cylinders cured beside the slab are tested to confirm it, because stressing too early can crush the concrete behind an anchorage.

Some designs call for a first stage of stressing soon after the pour, at a lower force, to hold the slab together while it begins to shrink. Full stressing follows once the concrete has reached the strength on the drawings.

The stressing

A hydraulic jack pulls each tendon to the force set in the design, and wedges lock the strand off in the anchorage. Two numbers get recorded for every tendon: the jack pressure and how far the strand stretched.

The measured extension is compared with the calculated one, and the specification sets how close they have to be. An extension outside that range is investigated before the tendon is accepted. A short one can mean extra friction or a blockage in the duct, and the cause is found before the slab is treated as finished.

Safety behind the jack

A stressed strand holds a very large force. If a wedge slips or a strand breaks, it can shoot out of the anchorage, so nobody stands behind the jack or in line with the anchorages during stressing, and the area is barricaded off.

Grout in the ducts

In a bonded system, the ducts are filled with cement grout after stressing. The grout bonds the strand to the concrete and protects it from corrosion, and the grouting records show each duct filled from end to end, with the air pushed out through vents.

The strand tails are then cut off and the stressing pockets at the slab edge are filled. That seals the anchorages against water, which matters most on a slab edge exposed to the weather.

Props and backprops

The props stay in until stressing is complete, because the tendons are part of how the slab holds itself up. Above a stressed slab, the floors still being built lean on it through backprops, and that sequence is part of the design, as set out in [backpropping and temporary works](/blog/backpropping-and-temporary-works).

Where a floor is poured in parts, the tendons stop at the joint or pass through it, and the stressing order follows, as covered in [construction joints in slabs and basement walls](/blog/construction-joints-in-slabs-and-basement-walls).

After handover

The tendon layout belongs with the building's records. Years later, someone will want to core a hole through the floor, and a cut tendon is a serious repair, so the slab is scanned and the tendons located first, as described in [core drilling and penetrations in existing slabs](/blog/core-drilling-and-penetrations-in-existing-slabs).

How we approach it

Our post-tensioning drawings show the tendon profile, the stressing sequence and the concrete strength needed at each stage. On site, we check the tendons before the pour and review the stressing records against the design before the props come out.

Once the pockets are filled, the tendon force can't be seen, so the stressing record is the only proof that it is there.

ACSES provides structural engineering, including post-tensioned slab design and construction supervision, across Sydney. Talk to us about a project.

Building Relationships Beyond Structures

George Khalil

George Khalil

Founder & Principal Engineer

almost three decades of structural, civil, and geotechnical engineering experience across 1,000+ projects.

Post-TensioningStressingConcrete SlabsSite SupervisionAS 3600

Tell us about your project.

We will respond with a clear understanding of how we can assist.

Partner With Us