A childcare centre inside a mixed-use building is classified as Class 9b under the National Construction Code, separate from the apartments, shops or offices around it. For the structure, the outdoor play area asks the most of the design, because on a podium or a roof it puts soil, soft fall, planters and play equipment on a suspended slab.

Two of our mixed-use projects include a centre. On Maroubra Road in Maroubra, a childcare centre of about 835 square metres sits in a building with 120 apartments over four basement levels. At Gateway Plaza on Old Northern Road in Baulkham Hills, a full level of childcare covering 656 square metres shares the building with five levels of commercial space and three retail units, over three basements.

The building class

Under the NCC, each part of a building takes its own class. Apartments are Class 2, offices Class 5, shops Class 6 and car parks Class 7a, while an early childhood centre is Class 9b, the class for assembly buildings.

The class drives the fire separation between the centre and the rest of the building. The fire engineer and the certifier set those requirements, and we design the slabs, walls and columns to hold the fire resistance they call for.

Floor loads

AS/NZS 1170.1 sets the load a floor is designed for according to how it is used. A childcare floor is designed for rooms full of children and staff, with furniture and storage, which is a heavier use than an apartment. A floor first designed for apartments gets checked before a centre moves onto it, the reasoning set out in [live loads and what a floor is designed for](/blog/live-loads-and-what-a-floor-is-designed-for).

Outdoor play on a slab

The national regulations for education and care services set a minimum outdoor play area for each child. In a building with no spare ground, that area often ends up on a podium or a roof terrace.

A play deck is one of the heaviest finishes a slab can carry. Soil in planters and garden beds is designed at its saturated weight, because it is wet after rain and after watering, and rubber soft fall, synthetic turf on its base layers, sandpits and fixed play equipment all add to it. The weights come from the play area design, and the earlier we have them, the sooner the slab thickness and the column loads are settled. The wider principles are in [green roofs and roof terraces](/blog/green-roofs-and-roof-terrace-loading).

A play deck sits over occupied space or a car park, so its waterproofing, falls and drainage outlets are designed with the slab. A set-down in the slab lets the drainage layer, soil and soft fall finish level with the indoor floor, so there is no step at the door.

Shade structures

Shade sails and shade structures over a play area catch the wind from underneath. Uplift often governs their posts, fixings and footings, the same issue covered in [carports, pergolas and patios](/blog/carports-pergolas-and-patios-engineering-certification). Every fixing into a waterproofed slab also needs a detail that keeps the membrane intact.

Barriers at the edge

Barriers around a play deck have to stop children falling, climbing over or squeezing through. Their geometry comes from the NCC, and the loads they resist come from AS/NZS 1170.1, with the posts fixed into a slab edge detailed to take them, as described in [balustrades and handrails](/blog/balustrades-and-handrails-structural-requirements).

Sound and footfall

Children at play over apartments or offices bring both sound and footfall vibration. The acoustic consultant sets the separation needed, and we coordinate the slab thickness and the floor build-up with them, so the centre and the homes below can both use the building as intended.

The rest of the building

Both buildings have post-tensioned floors, and both projects carried Specialist Engineering Assessments for Sydney Water. Gateway Plaza also needed engineering assessment reports for Transport for NSW. On both, our scope covered the shoring and underpinning design, dilapidation reports before and after construction, and the construction supervision and pre-pour inspections.

How we approach it

We ask for the centre's layout and the play area design as soon as the operator and the architect have them. The play deck loads decide the slab thickness, the set-downs and the columns underneath, so finding them late means redesigning a slab that is already drawn, or worse, already poured.

A play deck looks light from above, but the slab under it is carrying a garden.

ACSES provides structural engineering for mixed-use buildings with childcare centres across Sydney. Talk to us about a project.

Building Relationships Beyond Structures

George Khalil

George Khalil

Founder & Principal Engineer

almost three decades of structural, civil, and geotechnical engineering experience across 1,000+ projects.

ChildcareMixed-UseNCC Class 9bPlay DecksPodium Slabs

Tell us about your project.

We will respond with a clear understanding of how we can assist.

Partner With Us