Working Platforms For Piling Rigs And Cranes
A working platform is a layer of compacted crushed rock or gravel laid over the natural ground, giving a piling rig or a crawler crane firm footing for its tracks. It is designed for the heaviest pressure the rig puts on the ground, because if the platform gives way under one track, a tall rig can topple.
Piling rigs are heavy and top-heavy, and they work on sites that are half dug, wet or freshly filled. The platform is temporary, but it carries one of the most serious risks on the site.
Why the platform needs designing
A rig's weight sits on two tracks, and the pressure under them is far from even. When the mast goes up, the auger is pulled out of the ground or the rig slews with a load, the pressure shifts towards one edge of one track.
The ground has to carry that edge pressure without punching through. It is a bearing capacity problem with a thin, strong layer sitting over weaker ground, and the platform thickness comes out of that calculation.
What the design needs from the rig
The piling contractor supplies the track dimensions and the track pressures for each operation, such as standing, travelling, boring and extracting. The design takes the worst case and checks the platform for it.
A different rig turning up on the day changes the numbers. So the platform design names the rig it was designed for, and a heavier machine means a fresh check before it walks on.
The ground under the platform
The subgrade, the natural ground beneath the platform, does most of the work. Its strength comes from the geotechnical investigation and from testing on site.
Soft clay, old fill and wet ground all call for a thicker platform, a layer of geogrid within it, or treatment of the ground underneath, compared in [ground improvement techniques](/blog/ground-improvement-techniques-explained). The choice is usually a question of cost and of how quickly the rig needs to start.
Construction and testing
The platform material goes down in layers and is compacted, with testing as it goes in, the same discipline described in [controlled fill and compaction testing](/blog/controlled-fill-and-compaction-testing). Plate load tests on the finished surface confirm that it behaves the way the design assumed.
Before the rig walks onto it, the platform should be inspected and signed off against the design, for that rig and that area of the site.
What weakens a platform
Platforms fail at the places nobody planned for. A service trench dug through the platform and loosely backfilled, an old footing or tank removed and filled with spoil, a pile bore backfilled with loose material, or rainwater pooling on the surface all leave a soft spot under a track.
Edges are the other risk. A platform beside an excavation or a batter loses support on one side, so the rig stays back from the edge by a distance the design states.
Piling also produces spoil and slurry, and a platform churned up by tracks and covered in mud loses strength. Keeping it clean, drained and repaired is part of the routine while piling is under way.
Platforms inside a basement
Piles are often bored from the floor of a bulk excavation, and the rig then stands on clay or shale that has only just been exposed and is often wet. The platform goes over that surface, with the same design and testing.
The rig is also standing close to the shoring wall, so its load counts as a surcharge on the wall, the subject of [surcharge loads on retaining walls](/blog/surcharge-loads-on-retaining-walls). The shoring design and the platform design have to agree on how close the rig is allowed to get.
Cranes and outriggers
Crawler cranes need the same treatment as piling rigs. Mobile cranes set up on outriggers, which concentrate the load into four pads, and each pad needs ground or a mat that can carry it.
A mobile crane setting up beside a basement, or on a suspended slab, needs its outrigger loads checked against the shoring or the slab before it lifts. Tower cranes stand on their own designed base, a separate subject covered in [crane base design](/blog/crane-base-design-high-rise-construction).
How we approach it
We design working platforms as part of the geotechnical scope, on the same ground model as the piles they serve and with the rig loads from the piling contractor. Where the subgrade is weak, we would rather thicken the platform or improve the ground than rely on the weather staying dry.
The rig gets the attention on site, but the platform under it decides whether it stays upright.
ACSES provides geotechnical engineering, including rig working platforms and crane bases, across Sydney. Talk to us about a project.