Deep Basements And Towers In Campsie And Canterbury
The towers we have designed in Campsie and Canterbury sit over five, six and seven basement levels, with 31 to 40 storeys above them. At that depth the basement decides most of the engineering, and the shoring has to be solved before the typical floor matters.
The three are One Campsie on Beamish Street, with 40 storeys and 346 apartments over six basements, a 31-storey tower on London Street in Campsie over seven, and a 32-storey tower on Canterbury Road in Canterbury over five.
The ground
Both suburbs sit on Wianamatta Shale, the shale that covers much of Sydney west of the city. Near the surface it has weathered to clay, the shale gets harder with depth, and Hawkesbury Sandstone lies below it. Closer to the Cooks River the clay gives way to river alluvium, which is softer and holds water nearer the surface.
A basement seven levels deep goes a long way down through that profile, and the point where the shale turns to sandstone moves from one lot to the next. So the boreholes go below the bottom of the planned excavation, into the material the footings will stand on, rather than stopping at basement level. The thinking behind the numbers is in [how many boreholes a development site needs](/blog/how-many-boreholes-does-a-development-site-need).
The shoring wall
On a lot boxed in by shops and streets, there is no room to slope the sides of a dig this deep, so the wall goes in first. Bored piles socketed below the base of the excavation are a common answer in this ground, with shotcrete sprayed between them as each stage opens up. Exposed shale softens as it wets and dries, and the shotcrete stops a sound face from slowly breaking down once the weather gets to it.
The wall then needs support at each level as the excavator goes down, either from ground anchors drilled back under the land behind it or from props across the hole. We check every stage, not only the finished basement. A wall is often at its most exposed halfway down, with one more level dug and the next row of anchors not yet stressed. The anchor side is set out in [soil nailing and anchored retaining walls](/blog/soil-nailing-and-anchored-retaining-walls).
The buildings next door
Beamish Street and Canterbury Road are lined with older shops built close to their boundaries. A deep dig beside a shallow footing takes away the ground holding it up, unless the design deals with that first.
All three projects included the lateral support and underpinning design for the neighbouring buildings, with dilapidation reports before construction and again after it. Those reports are a plain record of the neighbours' cracks, levels and finishes, so any later claim gets checked against fact. The underpinning methods are covered in [underpinning adjoining structures](/blog/underpinning-adjoining-structures-explained).
Water at the lowest level
Shale lets little water through the rock itself. What does reach a deep basement tends to arrive along joints and bedding planes, and seven levels down, every litre of it has to be collected and pumped back up to the stormwater system, or kept out by a tanked structure designed for the water pressure.
Standpipe readings taken over time, along with the council's position on discharging groundwater, decide which way the design goes. The tanked option is described in [basement tanking and hydrostatic uplift](/blog/basement-tanking-and-hydrostatic-uplift).
The authorities
The railway line passes through both suburbs. All three towers needed engineering assessment reports for Transport for NSW, and the Canterbury Road tower needed them for Sydney Metro as well, each with its full calculation package. All three also needed Specialist Engineering Assessments for building close to Sydney Water assets.
The tower above
Every column and wall in a tower has to come down through the car park, so the column grid gets settled with the parking layout before the apartment plans are final. The two Campsie towers have post-tensioned floors, which keep the slabs thin over many storeys, and the Canterbury Road tower uses conventionally reinforced concrete.
Wind on a 40-storey building is carried down by the core and the shear walls, and the basement walls and slabs then take it into the ground. The basement is part of the tower's lateral system as well as its car park.
On site
We carried out the construction supervision and the pre-pour inspections on all three projects, checking the reinforcement against the drawings before each pour.
How we approach it
We treat the basement as the first structure on these sites. The shoring, the underpinning, the footings and the tower come from one team working on one ground model, and the reports for Sydney Water, Transport for NSW and Sydney Metro are written by the engineers who designed what those reports assess.
A tower in this ground is only as sound as the hole it stands in.
ACSES provides geotechnical engineering in Campsie and structural engineering in Canterbury. Talk to us about a project.