project structural engineer

Project: 278 Bunnerong Road Hillsdale

Work has begun on the project located at 278 Bunnerong Road Hillsdale. Meso Solutions are currently inserting sheet piles and bulk excavation works are set to take place shortly.

Great design by Nick Krikis and the architects at KTA. Bradley and the team at Jebeko have got things well and truly under control. ACSES Engineers are proud to be involved in this terrific development and honoured to be the Project Structural Engineer.

Project Specifications:

*   Three below ground basements
*   Two buildings on a common transfer slab
*   84 Residential Units in total

Our Scope of Works

*   Design and Detail the following:
*   Shoring & bulk excavation solution
*   Foundations solution
*   All concrete slabs
*   All concrete columns & walls
*   Specialist Engineering Assessment Report including full calculations package for Sydney Water
*   Shoring Report including full calculations package for Roads and Maritime Services
*   Dilapidation reports covering public assets and neighbouring properties


278 Bunnerong Road Hillsdale

 

Read more

Project: 538-540 Railway Parade Hurstville

The phone call went exactly like this…

Hello, George speaking…

“George… I just left Council and we are adding two extra levels on top”

But you’re forming up Level 1?

“I know… Architect will send you plans tomorrow”

Yes, but you’re in the process of forming the deck for Level 1?

“Ok cool… Architect will send you plans tomorrow… I’ll call you later”

The line went silent…

So imagine this:
• Foundations were built
• All the Basement 2 and Basement 1 structures were completed
• The Ground Floor main transfer deck was well and truly done
• And the boys on site were in the process of forming up the Level 1 slab

Suddenly we found ourselves needing to support an additional two levels of a structure that was not designed to carry an additional two levels.

This was going to be interesting, to say the least.

Using Finite Element Modelling (FEM), we were able to highlight weak areas of the existing structure that needed reinforcement as well as confirm areas that had sufficient strength to resist the new loads.

From the foundations to the supporting columns and walls to the suspended slabs, ACSES Engineers developed a total solution that enabled the extra levels to be added, while still maintaining the overall safety of the structure.

Below are some images of the carbon fibre reinforcement that were retrofitted to the soffit of the transfer slab. A terrific technology that gave us the extra strength we needed. Other strengthening works included widening and underpinning specific foundations as well as ‘beefing up’ specific columns and walls.

Shane and his team at First Class Building did an amazing job pulling it all together and the end result is a building that is safe, two storeys taller, and just about to be handed over to the various new owners.

Well done to all involved…

120332 - 538-540 Railway Parade Hurstville Image 2

120332 - 538-540 Railway Parade Hurstville Image 3

120332 - 538-540 Railway Parade Hurstville Image 4

120332 - 538-540 Railway Parade Hurstville Image 5

 

Read more

Project: 43-45 Beane Street Gosford

ACSES Engineers are honoured to have been appointed as the Project Structural Engineer for the project located at 43-45 Beane Street Gosford. We are incredibly excited to be part of the design team that will help deliver this exceptional development on the Central Coast.

Project Specifics

  • 3 Levels of Below Ground Basements
  • 1 Level of Commercial Suites
  • 18 Levels of Residential Units

Scope of Works includes the structural design of the following by our in-house Structural, Civil and Geotechnical Engineers:

  • Shoring and Foundation Solution
  • All retaining structures
  • All concrete slabs, stairs, ramps, columns and walls

For more information please contact us anytime.

Boarding House View 43-45 Beane Street Gosford

43-45 Beane Street Gosford Iamge 2

Read more

Project: Chiswick, New South Wales

An absolute joy to have been involved in this project. The client knew exactly what he wanted (and what he didn’t want). The builder was a genius. The architect – PL Projects – was focussed, firm, yet fair. And the team at ACSES Engineers just loved working on it.

ACSES Engineers designed both the bulk excavation solution and the various building structures. Utilising our finite element modelling (FEM) capabilities, we were able to eliminate the need for shoring works by taking advantage of the geotechnical parameters of the site. The FEM analysis verified that our vertical cut solution could safely be carried out without adversely impacting the neighbouring structures.

Again using our FEM expertise, ACSES Engineers designed the superstructure as a concrete framed solution made up of off-form reinforced concrete columns, walls and stairs. To achieve various parameters set by the architect, we designed the suspended slabs as post-tensioned solutions.

The level of detailing required for this master piece was ‘unbelievable’. From the concrete pool rising out of the ground with the infinity edges. To ‘the box’ suspended two levels over the Lower Ground Floor and cantilevering out 5m past its supports. To the off-form concrete walls almost 8m tall that needed to be poured in one go. To the ‘zig-zag’ stairs that could only be 100mm thick or the cantilevered stairs that could be no thicker than 110mm – the end results make all that work well worth the effort.

Congratulations to all involved.

ACSES Engineers are incredibly proud to have been part of the Design Team and honoured to have been the Project Structural Engineer for this development.

Chiswick New South Wales Image

Chiswick New South Wales Image 2 cropped

Chiswick New South Wales Image 3

Read more

Project: 1 Bede Street Strathfield

The structural frame at 1 Bede Street Strathfield has been completed, and the builder has done an amazing job in an incredibly short time.

General site specs:

  • Five Storey Building
  • Two below ground basements
  • 12 Residential Units

ACSES Engineers designed both the shoring and bulk excavation solutions, as well as the building superstructure.

Given the relative small size of the development, cost was a major driving factor for the client who gave us a very specific project brief – “fast, cheap and safe – make it happen”…

Utilising our finite element modelling capabilities, we were able to minimise the shoring works required to support the two level excavation face. Our modelling took advantage of the geotechnical parameters present at the site and ACSES Engineers were able to design a cantilevered pile wall solution with shotcrete infills.

Again using our FEM expertise, ACSES Engineers designed the superstructures as a concrete framed solutions made up of columns and walls using the Rediwall product wherever possible. This eliminated the need for traditional vertical formwork and resulted in further savings in time and cost. The slabs were all designed as conventionally reinforced slab solutions and the individual units were partitioned using lightweight non-load bearing walls made from fibre cement (Hebel) and framed Gyproc.

The project was architecturally designed by Ghazi Al Ali Architects and ACSES Engineers are proud to be part of the Design Team and honoured to be the Project Structural Engineer for this development.

1 Bede Street Strathfield Image 1

Read more

Project: 1 Villawood Place Villawood

Works are well underway at 1 Villawood Place Villawood and the team from Grandviewco have gotten off to an excellent start.

General site specs:

  • Nine Storey Building
  • Three below ground basements
  • Each basement level is over 2300m2
  • Ground Floor is over 2000m2 of commercial space
  • 119 Residential Units

ACSES Engineers designed both the shoring and bulk excavation solutions, as well as the building superstructure.

Utilising our finite element modelling capabilities, we were able to minimise the shoring works required to support the three level excavation face. All the basement levels were designed as conventionally reinforced slabs, while Ground Floor and Level 1 were designed as post tensioned solutions. All these levels were supported on traditionally formed and reinforced concrete walls and columns. Working with our design partners from Ultrafloor and AFS Systems, ACSES Engineers designed all the upper levels as a load bearing wall – concrete framed solution. From Level 1 upwards, AFS Logic Wall was used to support the Ultrafloor slab system, from Level 2 onwards. This construction process was adopted by Grandviewco to eliminate the need for traditional formwork as much as possible. To partition the units, lightweight non-load bearing walls made from fibre cement (Hebel) and framed Gyproc were used.

The project was architecturally designed by Tony Owen Partners and ACSES Engineers are proud to be part of the Design Team and honoured to be the Project Structural Engineer for this development.

Here is the 3D Perspective.

1 Villawood Place Villawood 3D

Read more

Project: 5-7 Telegraph Road Pymble

ACSES Engineers designed a shoring and bulk excavation solution that extended four levels below 5-7 Telegraph Road Pymble as well as the superstructures.

Below are some site specs:

  • Two buildings over common basement carparking
  • Three below ground basements
  • Each Basement level is over 2100m2
  • 47 Residential Units

Utilising our finite element modelling capabilities, we significantly reduced the required shoring works at 5-7 Telegraph Road Pymble by designing an anchored pile and shotcrete wall to support the excavated face above the Class IV material, and then vertically cut the rock strata down to the bulk excavation level.

We also designed the crane base, without requiring piles, to bear directly on the Class IV material located higher than the final bulk excavation level. This shoring and bulk excavation solution designed by ACSES Engineers resulted in massive cost and time savings for South West Builders, who must be congratulated on successfully carrying out the detailed works.

Again using our FEM expertise, ACSES Engineers designed the superstructures as a concrete framed solutions made up of columns and walls using the Dincel Wall product wherever possible. This eliminated the need for traditional vertical formwork and resulted in further savings in time and cost for the builder. To partition the units, lightweight non-load bearing walls made from fibre cement (Hebel) and framed Gyproc were used.

The project was architecturally designed by Aleksander Design Group and ACSES Engineers are proud to be part of the Design Team and honoured to be the Project Structural Engineer for this development.

5-7 Telegraph Road Pymble Image 1

5-7 Telegraph Road Pymble Image 2

5-7 Telegraph Road Pymble Image 3

5-7 Telegraph Road Pymble Image 5

5-7 Telegraph Road Pymble Image 6

5-7 Telegraph Road Pymble Image 7

5-7 Telegraph Road Pymble Image 8

Here is the 3D Perspective.

5-7 Telegraph Rd Pymble 3D

Read more

Project Update: 100 Castlereagh Street Liverpool

Thanks for all the fantastic feedback.

Below are some site specs:

  • Four below ground basements
  • Each Basement is over 3300m2
  • 2 Commercial Levels
  • 25 Residential Levels – 298 Units

Here are some more images from the site:

100 Castlereagh Street Liverpool Image 1

100 Castlereagh Street Liverpool Image 2

100 Castlereagh Street Liverpool Image 3

100 Castlereagh Street Liverpool Image 4

100 Castlereagh Street Liverpool Image 5

100 Castlereagh Street Liverpool Image 6

100 Castlereagh Street Liverpool Image 7

100 Castlereagh Street Liverpool Image 8

100 Castlereagh Street Liverpool Image 9

100 Castlereagh Street Liverpool Image 10

100 Castlereagh Street Liverpool Image 11

Read more

Project Spotlight: 2A-8 Burwood Road Burwood

Shoring and bulk excavation works at 2A-8 Burwood Road Burwood have been completed and foundation works have begun. It’s a tight, detailed site, but the COPLEX Constructions team have everything running smoothly like a well-oiled machine. ACSES Engineers are proud to be part of the Design Team and honoured to be the Project Structural Engineer.

2A-8 Burwood Road Burwood Image 1

Here is the 3D Perspective.

2A-8 Burwood Road Burwood

Read more

Project Spotlight: 75-83 Second Avenue Campsie

Sheet Piles are in and bulk excavation works at 75-83 Second Avenue Campsie have now begun. Sam and the team at SWEDA have got it all under control and congratulations to Balintore Developments on yet another great project. ACSES Engineers are proud to be part of the Design Team and honoured to be the Project Structural Engineer for this development.

75-83 Second Avenue Campsie

Here are the 3D Perspectives.

75-83 Second Avenue Campsie Image 2

Read more