Work-As-Executed Drawings And Engineering Handover

George KhalilFounder & Principal Engineer5 min read

Work-as-executed drawings, often called as-built drawings, record what was built on a site, as opposed to what the design drawings intended. They matter at handover, because the council and the certifier ask for some of them before a building can be occupied, and they matter for decades afterwards, because every later alteration starts from them.

Why the built work differs

No building goes up exactly as drawn. A pipe moves to miss a footing, a pit ends up lower than planned, a pile goes deeper because the rock was lower than the boreholes showed, or an RFI changes a detail during construction.

Each of those is fine once it has been approved. The drawings at the end still need to show it, and the process behind those approvals is set out in [who is responsible when a design changes on site](/blog/who-is-responsible-when-a-design-changes-on-site).

Civil works

On the civil side, work-as-executed plans come from a survey of what went into the ground. They show the pit and pipe levels, the on-site detention tank with its volume and outlet, and the finished surface levels across the site.

Councils commonly ask for work-as-executed plans of the stormwater system and the on-site detention, along with an engineer's certificate that it works as designed, before the occupation certificate is issued. The design side of those systems is covered in [stormwater management for Sydney sites](/blog/stormwater-management-sydney-sites-osd-infiltration-compliance). Where water or sewer assets were built through Sydney Water's process, Sydney Water asks for its own as-built records as well.

Structural records

For the structure, the record is the final drawing set with every approved site change included. Behind it sit the records gathered during construction: pre-pour inspection reports, concrete test results, pile logs and, on post-tensioned floors, the stressing and grouting records described in [stressing a post-tensioned slab](/blog/stressing-a-post-tensioned-slab).

Those records also support the certificates an engineer issues at the end, the process covered in [structural certification and inspection certificates in NSW](/blog/structural-certification-and-inspection-certificates-nsw).

Who prepares them

A surveyor measures the civil work as it was built. The builder supplies the records from site, and the engineer reviews them against the design, updates the drawings for the changes that were approved, and certifies the work where the certifier asks for it.

The engineer's part is the check. A surveyed plan shows where a pipe or a tank ended up, but only a comparison with the design shows whether it still does what the design needed, such as holding the right volume of water or draining at the right grade.

Where handover goes wrong

Records collected at the end are harder to get than records kept as the work goes. A pit level surveyed after the paving goes down has to be dug up to check, and a stressing record lost from a site office can't be recreated after the stressing crew has left.

Changes made without telling the engineer are the other gap. If nobody raised an RFI, there is no approved change to draw, and the certifier is left with work that matches neither the design nor any revision of it.

After handover

The owner keeps the set, or the owners corporation in a strata building. An engineer looking at a new opening, a leak in the basement, a mezzanine or new plant on the roof starts from those drawings and records, and a building with a complete set costs far less to investigate than one without.

How we approach it

We keep the record as the project goes. Each RFI answer and drawing revision is logged against the sheet it changes, and inspection reports are filed as they are issued, so the handover set comes together from records that already exist. At handover, the final drawings carry every approved change, and the certifier and the owner both get the same account of what was built.

The design drawings show what was meant, and the work-as-executed set shows what is there, which is the one the next engineer will need.

ACSES provides project management, including handover documentation and as-built coordination, with structural and civil engineering across Sydney. Talk to us about a project.

Building Relationships Beyond Structures

George Khalil

George Khalil

Founder & Principal Engineer

almost three decades of structural, civil, and geotechnical engineering experience across 1,000+ projects.

Work-As-ExecutedAs-Built DrawingsHandoverCertificationStormwater