project update

Project: 278 Bunnerong Road Hillsdale

Work has begun on the project located at 278 Bunnerong Road Hillsdale. Meso Solutions are currently inserting sheet piles and bulk excavation works are set to take place shortly.

Great design by Nick Krikis and the architects at KTA. Bradley and the team at Jebeko have got things well and truly under control. ACSES Engineers are proud to be involved in this terrific development and honoured to be the Project Structural Engineer.

Project Specifications:

*   Three below ground basements
*   Two buildings on a common transfer slab
*   84 Residential Units in total

Our Scope of Works

*   Design and Detail the following:
*   Shoring & bulk excavation solution
*   Foundations solution
*   All concrete slabs
*   All concrete columns & walls
*   Specialist Engineering Assessment Report including full calculations package for Sydney Water
*   Shoring Report including full calculations package for Roads and Maritime Services
*   Dilapidation reports covering public assets and neighbouring properties


278 Bunnerong Road Hillsdale

 

Read more

Project Update: 100 Castlereagh Street Liverpool

Thanks for all the fantastic feedback.

Below are some site specs:

  • Four below ground basements
  • Each Basement is over 3300m2
  • 2 Commercial Levels
  • 25 Residential Levels – 298 Units

Here are some more images from the site:

100 Castlereagh Street Liverpool Image 1

100 Castlereagh Street Liverpool Image 2

100 Castlereagh Street Liverpool Image 3

100 Castlereagh Street Liverpool Image 4

100 Castlereagh Street Liverpool Image 5

100 Castlereagh Street Liverpool Image 6

100 Castlereagh Street Liverpool Image 7

100 Castlereagh Street Liverpool Image 8

100 Castlereagh Street Liverpool Image 9

100 Castlereagh Street Liverpool Image 10

100 Castlereagh Street Liverpool Image 11

Read more

Project Update: 153-165 Brougham Street Potts Point

Bulk excavation works at 153-165 Brougham Street Potts Point are coming to an end, and foundation works have begun. The crane is up and running and our ‘modified hybrid’ crane base design is working well. It’s a tight, detailed site, but the Reform team have everything well under control and moving like clockwork. ACSES Engineers are proud to be part of the Design Team and honoured to be the Project Structural Engineer.

153-165 Brrougham Street Potts Point

Here are the 3D Perspectives.

Read more